The implementation of The Planning (Scotland) Act 2019 (“the 2019 Act”) rumbles on, and 1st of October marked the latest milestone in its series of reforms.

Two new instruments are now in force:

  • the Town and Country Planning (Pre-Application Consultation) (Scotland) Amendment Regulations 2021 (the “PAC Regulations”); and
  • the Planning (Scotland) Act 2019 (Commencement No. 9 and Saving and Transitional Provisions) Regulations 2022 (the “Commencement Regulations”).

So, what’s changed?

Pre-application consultation (“PAC”)

PAC is a statutory requirement which applies to applicants for “major” and “national” development. It involves holding at least one public event where members of the public may make comments on a prospective applicant’s development proposal.

From 1st October, the PAC regulations require:

  • A minimum of two public events to be organised by the applicant;
  • Newspaper notices to be placed by the applicant in relation to each such statutory public event (and indicating where additional information can be obtained and how comments can be made to the prospective applicant);
  • Consultation with relevant community councils;
  • Feedback to be provided at the final public event;
  • Compliance with new statutory requirements on the content of the PAC report;
  • New exemptions to PAC requirements in certain cases (i.e., where a proposal for essentially the same development has been through PAC before and an earlier application was then made within the previous 18 months), and
  • A statutory limit of 18 months between a Proposal of Application Notice (“POAN”) being submitted to the planning authority and the subsequent application.

This last change is particularly important. Whilst previously a period of at least 12 weeks had to pass between submission of the POAN and submitting the application (and this is still the case), no maximum period was prescribed. The change means that failure to submit an application within 18 months of a POAN will result in having to repeat the PAC process, starting with a new POAN. For those POANs submitted prior to these changes coming into effect, the 18-month period will begin on 1st October 2022, meaning that prospective applicants will have until March 2024 to submit the related application.

Duration of planning permission and planning permission in principle (Section 58 and 59 of the 1997 Act)

Previously, section 58 of the Town and Country Planning (Scotland) Act 1997 (“the 1997 Act”) provided a statutory limitation of three years for the duration of planning permission, with the option for planning authorities to direct that a different period applied (which could be longer or shorter than three years).

For planning permission in principle, section 59 of the 1997 Act provided a statutory limitation of three years for an approval of matters specified in conditions, and two years thereafter for implementing the permission.

From 1st October, the duration is to be specified in a condition attached to the permission.

For planning permission, the default period will be three years, unless the planning authority specify a different duration. For planning permission in principle, the default period will be a single period of five years, unless otherwise specified.

Timescales for approval of matters specified in condition (Section 59 of the 1997 Act)

Previously, the time periods for making applications for approval of matters specified in conditions were specified in the 1997 Act.

From 1st October, this statutory framework is removed, and it is for planning authorities to consider such periods and specify them in conditions.

Completion notices (Section 61 and 62 of the 1997 Act)

Planning authorities may issue a notice requiring completion of a development.

From 1st October, it is no longer a requirement for the Scottish Government to confirm every such notice, thus streamlining the process.  Instead, those wishing to appeal a completion notice served on or after 1st October will now be able to lodge an appeal with the Scottish Government. An applicant must be given at least 28 days to lodge their appeal, and the time period should be specified on the completion notice.

Declining to determine a planning application (Section 39 of the 1997 Act)

Planning authorities have discretion to refuse to determine ‘repeat’ planning applications in certain circumstances.

From 1st October, the period for which that discretion applies is extended from two to five years.

New Circular on Development Management Procedures

On 21st October, the Scottish Government published a new Development Management Procedure Circular which provides guidance on the recent changes.

What next and when?

These recent changes are important.

However, significant reform is yet to come.

Highly anticipated is Scotland’s fourth National Planning Framework (“NPF4”). The public consultation on Draft NPF4 closed on 31st March 2022. The Scottish Government intends to set out a revised draft for the Scottish Parliament’s consideration and approval in the autumn, and to progress its adoption by Ministers thereafter.

Also yet to be brought into effect are key provisions relating to (among others):

  • Master Plan Consent Areas;
  • Removal of the requirement to prepare strategic development plans;
  • Schemes of Delegation;
  • Appeals, and
  • Local Reviews.

The reform of Scotland’s planning system continues. In the meantime, the Transforming Planning website will continue to be a useful tool for following progress.

If you would like more information or advice on planning matters, please get in touch – our specialist Planning team would be delighted to help.

Written by

Related News, Insights & Events

Court Of Session Revokes Rosebank And Jackdaw Consents

Court of Session rules on Rosebank and Jackdaw consents

The Outer House of the Court of Session has taken a notable decision on both the consent for the Rosebank oil and gas field and the consent for the Jackdaw gas field.

Read more
Building Safety In Scotland Legislation Comes Into Force On 6 January 2025

Building safety in Scotland: Legislation comes into force on 6 January 2025

The Act was introduced by the Scottish Government to reduce the risk to life from unsafe cladding on high-rise homes.

Read more
LOI Website

Letters of Intent in construction projects: Practical insights

Letters of intent (LOI) are widely used in the construction industry. Here we explore what LOIs are, their role in the industry and how they can be used effectively.

Read more

Want to hear more from us?

Subscribe here